Part 9 Buildings After December 15 2017

For Residential Buildings Greater than 1200 sq.ft.:

Newly-constructed residential buildings are required to meet Step 2 of the BC Energy Step Code. 

Building Permit Applications must include:

  1. A completed Design Verification Report
  2. A completed House Performance Report (Pre-Construction)
  3. Energy Model (example: HOT2000 detailed report)
  4. EnerGuide Homeowner Information Sheet (if applicable)

Prior to Final Inspection:

  1. A completed House Performance Report (As-Built) must be provided to the Building Inspector

For Residential Buildings Less than or Equal to 1200 sq.ft.:

Newly-constructed small residential buildings must show compliance with Section 9.36 of the BCBC.  Building Permit Applications must include (at least):

 

For non-Residential Buildings:

Newly-constructed non-residential buildings must show compliance with Section 9.36 of the BCBC.  Building Permit Applications must include (at least):

  1. A completed Design Verification Report